News Release

The CJ Group Project in the Philippines

Date:2018-05-02 Source: Author: Browse: Font:LargeMediumSmall Print

The feed plant was the first overseas project CJ Group contracted FAMSUN to build in the Philippines. All the equipment ranging from steel structure workshop, steel structure warehouses to silos was manufactured by FAMSUN.


The construction began on July 30, 2017 and was complete on December 11, 2017. Despite the challenges brought forth by the rainy season in the Philippines, frequent blackout at the construction site and the visa issue, the construction team of FAMSUN managed to wrap up all the work before the deadline.